Text of Recommendation | To ensure the safety and security of Pol-i-Charkhi prison’s inmates and workers and to ensure the U.S. government receives the highest value for its contract dollars, SIGAR recommends that the Secretary of State direct INL to: Conduct a cost-benefit analysis of alternative wastewater management systems and, if warranted, reissue an RFI soliciting proposed solutions to the prison’s wastewater management needs. |
---|---|
Recommendation Status | Closed |
Recommendation Questioned Costs | $0 |
Recommendation Funds for Better Use | $0 |
Submitting OIG | |
---|---|
Report Title | Pol-i-Charkhi Prison: After 5 Years and $18.5 Million, Renovation Project Remains Incomplete |
Report Submitting OIG-Specific Report Number | 15-11-IP |
Report Date Issued | Friday, October 17, 2014 |
Report Questioned Costs | $0 |
Report Funds for Better Use | $0 |