Text of Recommendation | We recommend that the Commander of U.S. Forces–
Afghanistan (USFOR-A) notify the Afghan Ministry of Public Works of the deficiencies and maintenance issues
with the road and bridge—specifically, support beams with honeycombing; shorter than required stone barriers,
protective retaining walls, and protective railings; missing protective walls around culverts; and broken stone
masonry and uncleared debris around culverts—so the ministry can take action to correct them. |
---|---|
Recommendation Status | Closed |
Recommendation Questioned Costs | $0 |
Recommendation Funds for Better Use | $0 |
Submitting OIG | |
---|---|
Report Title | Afghanistan’s Ghulam Khan Road Project: Construction of the Road and Bridge Generally Met Contract Requirements, but Deficiencies Have Created Safety Hazards for Users |