Text of Recommendation | Develop, document, and implement an internal control process to apply when an OA is planning to acquire or continue to occupy an office space that exceeds the Agency's utilization standard. At a minimum, the process should require the OA to justify with documented evidence that it has implemented a different standard based on mission requirements or that applying the Department's standard will not be cost-effective or a best value option. Implementing this recommendation could potentially put $2.1 million in funds to better use by preventing DOT from paying for unneeded space that exceeds the Agency's utilization standard. |
---|---|
Recommendation Number | 2 |
Recommendation Status | Open |
Significant Recommendation | Yes |
Recommendation Questioned Costs | $0 |
Recommendation Funds for Better Use | $2,100,000 |