Text of Recommendation | Based on the results of the audit, SIGAR recommends that the Mission Director of USAID/AfghanistanReview the results of ARD’s IT equipment and software purchase analysis and recover any ineligible costs identified. |
---|---|
Recommendation Status | Closed |
Recommendation Questioned Costs | $0 |
Recommendation Funds for Better Use | $0 |
Submitting OIG | |
---|---|
Report Title | USAID’s Afghan Sustainable Water Supply
and Sanitation Project: Audit of Costs
Incurred by ARD, Inc. |
Report Submitting OIG-Specific Report Number | 15-28-FA |
Report Date Issued | Tuesday, January 13, 2015 |
Report Agency Reviewed / Investigated | |
Report Questioned Costs | $0 |
Report Funds for Better Use | $0 |