Audit of the U.S. Nuclear Regulatory Commission’s (NRC) Cybersecurity Inspection Program for Operating Nuclear Power Plants

2026
OIG-NRC-26-A-03
Audit
Nuclear Regulatory Commission OIG
Nuclear Regulatory Commission

The OIG determined that the current cybersecurity program guidance lacks clarity; expectations for maintaining training qualifications are not well-defined; the cybersecurity inspection process contains redundant and time-consuming tasks; and NRC staff members did not always accurately report their...

Audit of the U.S. Nuclear Regulatory Commission’s Qualification Programs

2025
OIG-NRC-25-A-13
Audit
Nuclear Regulatory Commission OIG
Nuclear Regulatory Commission

The U.S. Nuclear Regulatory Commission (NRC) does not have an adequate process for managing, tracking, and monitoring staff qualification records. The OIG found that NRC offices use inconsistent information-gathering methods, driven by changes in management’s workforce planning and individual office...

Audit of the U.S. Nuclear Regulatory Commission’s Awards and Recognition Program

2025
OIG-NRC-25-A-12
Audit
Nuclear Regulatory Commission OIG
Nuclear Regulatory Commission

The Office of the Inspector General (OIG) found that the U.S. Nuclear Regulatory Commission (NRC) generally administered performance awards effectively; however, the OIG identified deficiencies in administering special act awards that require improvement. Specifically, the NRC granted special act...