(U) Rec. A.1.b: The DoD OIG recommended that the Commanding General, Marine Corps Base Camp Pendleton, direct master planners to update installation Master Plans to include Unified Facilities Criteria 2-100-01, "Installation Master Planning," September 30, 2020 climate change requirements, using information from the completed climate assessment.
Questioned Costs
$0
Funds for Better Use
$0
Recommendation Status
Open
Source UUID
DODIG-2024-100-D-2024-0100-D000RL-0001-0001.A1b
Report
Recommendation Number
D-2024-0100-D000RL-0001-0001.A1b
Significant Recommendation
No