| Text of Recommendation | We recommend the Senior Vice President, Power Operations, remove the decommissioned asset from the network and follow the operational technology asset inventory validation as required by Power Operations’ Standard Operating Procedure 12.862. |
|---|---|
| Recommendation Number | 2 |
| Recommendation Status | Open |
| Significant Recommendation | No |
| Recommendation Questioned Costs | $0 |
| Recommendation Funds for Better Use | $0 |
| Submitting OIG | |
|---|---|
| Linked Report |