| Text of Recommendation | We recommend the Architect of the Capitol (AOC) require the Construction Manager as Constructor (CMc) to submit a final Testing, Adjusting and Balancing report. If the CMc is unable to do so, the AOC should assess a credit against the CMc for failing to properly complete its contractual obligations. |
|---|---|
| Recommendation Number | 4 |
| Recommendation Status | Open |
| Significant Recommendation | No |
| Recommendation Questioned Costs | $0 |
| Recommendation Funds for Better Use | $0 |
| Submitting OIG | |
|---|---|
| Linked Report |