| Text of Recommendation | We recommend the Architect of the Capitol recovers or not award the questioned costs of $3,551 identified within the Exterior Stone & Metal Preservation, Phase III project to the extent legally and administratively possible and ensure the contractor excludes subcontractor profit prior to applying contractual markups. |
|---|---|
| Recommendation Number | 8 |
| Recommendation Status | Open |
| Significant Recommendation | No |
| Recommendation Questioned Costs | $0 |
| Recommendation Funds for Better Use | $3,551 |
| Submitting OIG | |
|---|---|
| Linked Report |