| Text of Recommendation | We recommend that the Director of HUD's Buffalo Office of Community Planning and Development reimburse from non-Federal funds $162,923 ($134,711 $28,212) expended on ineligible costs pertaining to street improvement projects not done and a duplicate reimbursement. |
|---|---|
| Recommendation Number | 2011-NY-1010-001-B |
| Recommendation Status | Open |
| Recommendation Questioned Costs | $162,923 |
| Recommendation Funds for Better Use | $0 |
| Submitting OIG | |
|---|---|
| Report Title | The City of Buffalo Did Not Always Administer Its Community Development Block Grant Program in Accordance With HUD Requirements |
| Report Submitting OIG-Specific Report Number | 2011-NY-1010 |
| Report Date Issued | Friday, April 15, 2011 |
| Report Questioned Costs | $0 |
| Report Funds for Better Use | $0 |