Text of Recommendation | Rec. 3.b: The DoD OIG recommended that the F-35 Program Executive Officer direct F-35 Program Office officials, in coordination with the Defense Contract Management Agency and the prime contractor, before a decision to begin full-rate production of the F-35 is made, upon completion of Recommendation 3.a, ensure contractor-acquired property procured on past contracts is transitioned to Government-furnished property on contracting actions as required by the Defense Federal Acquisition Regulation Supplement. |
---|---|
Recommendation Number | D-2019-0062-D000RK-0001-0003.b |
Recommendation Status | Open |
Significant Recommendation | No |
Recommendation Questioned Costs | $0 |
Recommendation Funds for Better Use | $0 |
Submitting OIG | |
---|---|
Linked Report |