Text of Recommendation | For the $143 million in PE projects questioned in this report without adequate justification for time extensions or avoided repayments, obtain from the States appropriate support or repayment of PE expenditures as required.
|
---|---|
Recommendation Number | 7 |
Recommendation Status | Open |
Significant Recommendation | Yes |
Recommendation Questioned Costs | $143,000,000 |
Recommendation Funds for Better Use | $0 |
Additional Details Link |
Submitting OIG | |
---|---|
Report Title | FHWA Does Not Effectively Ensure States Account for Preliminary Engineering Costs and Reimburse Funds as Required |
Report Submitting OIG-Specific Report Number | ST2016095 |
Report Date Issued | Thursday, August 25, 2016 |
Report Agency Reviewed / Investigated | |
Report Questioned Costs | $143,000,000 |
Report Funds for Better Use | $4,400,000,000 |